Main Street is closed between Pike and Madison Streets for its reconstruction project.

The main part of the project begins May 4, with the milling of the existing pavement. During the milling and the placement of the new pavement, Main Street will be closed to traffic and on-street parking. This is required due to the depth of the milling and paving process.

Main Street will be fully closed May 4 through the 16th.

Beginning May 18, lane restrictions will be required to install the new pavement markings. One side of the roadway will be installed before switching to the other side.

During the Main Street closure, the angled parking on Jefferson Street, Washington Street and Clinton Street will be temporarily changed to perpendicular parking.  The existing pavement markings will not be changed but the City of Goshen Street Department will place signs to inform the traveling public.

For more updates, go to goshenindiana.org/main-street or follow the City’s Facebook Page at facebook.com/CityOfGoshen.